Main Article Content

Abstract

The Role of Variance Analysis as a Project Costs Controlling Tool
Purpose:
To analyse the role of variance analysis as a cost control tool for controlling project costs which was implemented during the Covid-19 pandemic.


Method: Quantitative with a case study approach.


Result: Variance analysis can be used as a cost control tool for Road Rehabilitation projects during the Covid-19 pandemic. Using variance analysis, it can be seen that the existence of the Covid-19 pandemic has affected the company's operating costs, indicated by the presence of unfavorable and favorable projects.


Novelty: Variance analysis can be used to identify areas where project cost deviations occurred during the Covid-19 pandemic.


Contribution: Management can use variance analysis to anticipate significant cost changes in the construction sector


Peran Analisis Varians Sebagai Alat Pengendalian Biaya Proyek
Tujuan: mengkaji peran analisis varians sebagai alat pengendalian biaya proyek  yang pelaksanaannya terjadi pada pandemi Covid-19.


Metode: Kuantitatif dengan pendekatan studi kasus.


Hasil: Variance analysis bisa digunakan sebagai alat pengendalian biaya proyek Rehabilitasi Jalan pada saat pandemic Covid-19. penggunaan variance analisis dapat dilihat bahwa keberadaan Pandemi Covid-19 telah memengaruhi biaya operasional perusahaan, ditunjukkan dengan adanya varians tidak menguntungkan dan menguntungkan dalam pelaksanaan proyek. 



Kebaruan: Analisis varians bisa digunakan sebagai idintifikasi area mana yang terjadinya penyimpangan biaya proyek saat pandemi Covid-19.


Kontribusi: Pihak manajemen bisa menggunakan variance analysis untuk mengantisipasi terjadinya perubahan biaya yang signifikan di sektor konstruksi.

Keywords

Variance analysis Project cost Cost control

Article Details

References

  1. B.-S. Indonesia, Indikator Konstruksi, Triwulanan IV-2021. Jakarta, 2022. [Online]. Available: https://www.bps.go.id/publication/2022/04/08/8134ad6132fceecf0daea331/indikator-konstruksi-triwulanan-iv-2021.html
  2. S. Elvira, M. M. Fadjar, and A. Sudarma, “Analisis Perencanaan Dan Pengendalian Biaya Operasional Dalam Rangka Meningkatkan Laba Pada Pt. Pratama Citra Bersinar,” Atma Jaya Account. Res., vol. 4, no. 01, pp. 40–47, 2021, doi: 10.35129/ajar.v4i01.167.
  3. O. Adebayo, I. Lawrence, and A. T. Sola, “Budgetary Control : A Tool for Cost Control in Manufacturing Companies in Nigeria,” Eur. J. Econ., vol. 6, no. 37, pp. 98–109, 2014.
  4. C. Sarah and E. E. Sembiring, “Evaluation of the Role of Operational Costs Budget as Management Control Tool ( Case Study in PD Lima Motor Garut ),” Indones. Account. Lit. J., vol. 02, no. 01, pp. 12–25, 2021, [Online]. Available: https://jurnal.polban.ac.id/ojs-3.1.2/ialj/article/view/3175
  5. H. Hakimah, “Analisis Peranan Anggaran Sebagai Alat Perencanaan dan Pengendalian Biaya Proyek Pada CV. Anugerah Jaya Surabaya,” Sustainable, vol. 1, no. 1, p. 84, 2021, doi: http://dx.doi.org/10.30651/stb.v1i1.9699.
  6. A. H. D. Sanputra, “Analisis Rencana Anggaran Biaya (Rab) Proyek Sebagai Alat Perencanaan Dan Pengendalian Biaya (Studi Kasus Pada Pt. Griya Sentosa Property),” J. Ilm. Mhs. Fak. Ekon. dan Bisnis Univ. Brawijaya, vol. 4, no. 1, 2005, [Online]. Available: https://jimfeb.ub.ac.id/index.php/jimfeb/article/view/2400/2185
  7. G. S. Klychova, М. S. Faskhutdinova, and E. R. Sadrieva, “Budget Efficiency for Cost Control Purposes in Management Accounting System,” Mediterr. J. Soc. Sci., vol. 5, no. 24, pp. 79–83, 2014, doi: 10.5901/mjss.2014.v5n24p79.
  8. O. B. Latunggamu, H. Karamoy, and M. Kalalo, “Analisis Anggaran Proyek Sebagai Alat Pengendalian Biaya Pada Pt Esta Group Jaya Manado,” J. EMBA J. Ris. Ekon. Manajemen, Bisnis dan Akunt., vol. 9, no. 2, pp. 876–882, 2021, doi: https://doi.org/10.35794/emba.v9i2.33843.
  9. H. R. Antoro and M. S. Wibowo, “Evaluation of Budgeting Process for Infrastructure Investment Project in Manufacturing Companies,” Proc. Int. Conf. Econ. Manag. Account. (ICEMAC 2021), vol. 207, no. Icemac 2021, pp. 18–29, 2022, doi: 10.2991/aebmr.k.220204.003.
  10. N. Astuti, O. Oktariansyah, and S. Puspita, “Analisis Perencanaan dan Pengendalian Biaya Proyek Pada CV. Indo Truss Perdana Prabumulih,” J. Media Akunt., vol. 4, no. 1, pp. 80–96, 2021, doi: 10.31851/jmediasi.v4i1.7269.
  11. N. B. S. Marpaung, S. Elviani, Z. Siregar, and A. Rasyid, “Peranan Anggran Biaya Produksi Dalam Meningkatkan Efektivitas Dan Efesiensi Pengendalian Biaya Produksi Pada Pt. Tolan Tiga Indonesia,” JRAM (Jurnal Ris. Akunt. Multiparadigma), vol. 8, no. 1, pp. 77–84, 2021, doi: 10.30743/akutansi.v8i1.4068.
  12. F. M. Luan, L. D. Ekasari, and A. Mukoffi, “Analisis Anggaran Biaya Operasional Dan Anggaran Pendapatan Terhadap Kinerja Keuangan Berdasarkan Return On Asset ( ROA ) Pada Counter Crocs TM Di Kota Malang,” J. Mutiara Akunt., vol. 6, no. 2, pp. 158–165, 2021, doi: https://doi.org/10.51544/jma.v6i2.1963.
  13. D. Palijama, “Analisis Anggaran Proyek Sebagai Alat Pengendalian Biaya Dan Kinerja Pada Cv. Putra Papua Sejahtera,” J. Pitis AKP, vol. 2, no. 1, pp. 39–55, 2018, doi: http://dx.doi.org/10.32531/jakp.v3i1.90.
  14. R. Nugroho, S. Hardjomuljadi, and M. Amin, “Dampak Pendemi Covid-19 Atas Timbulnya Klaim Waktu Dan Biaya Pada Proyek-Proyekpembangkit Listrik Di Indonesia,” vol. 14, no. 1, pp. 18–32, 2022, doi: https://doi.org/10.24853/jk.14.1.18-32.
  15. W. Soviana, H. A. Rani, and R. A. Rahman, “Dampak Covid-19 Terhadap Pelaksanaan Pekerjaan Konstruksi Multi Years,” sIKLU s J. Tek. Sipil, vol. 8, no. 1, pp. 11–23, 2022, doi: https://doi.org/10.31849/siklus.v8i1.8627.
  16. M. Ogunnusi, M. Hamma-adama, H. Salman, and T. Kouider, “COVID-19 pandemic : the effects and prospects in the construction industry .,” Int. J. Real Estate Stud., vol. 14, no. 2, pp. 120–128, 2020, [Online]. Available: https://www.utm.my/intrest/files/2020/11/2_Final_MS_CRES-Covid-025.pdf
  17. Sugiyono, Metode Penelitian Kuantitatif, Kualitatif, Dan R&D. Bandung: Alfabeta, 2017.
  18. M. Nafarin, Penganggaran Perusahaan, 3rd ed. Jakarta: Selemba Empat, 2013.
  19. S. B. Henong, “Dampak Pandemi Covid-19 terhadap Penyelesaian Proyek Konstruksi : Tinjauan Literatur Sistematis,” vol. 2, no. 1, pp. 23–29, 2022.
  20. J. Clarita and B. Anondho, “Peringkat Faktor-Faktor Yang Mempengaruhi Produktivitas Konstruksi Akibat Penyebaran Virus Covid-19,” JMTS (Jurnal Mitra Tek. Sipil ), vol. 5, no. 1, pp. 223–232, 2022, doi: https://doi.org/10.24912/jmts.v5i1.16852.
  21. Bevananda, “Dampak Pandemi Corona Didalam Bisnis Konstruksi,” PT. Bevananda Mustika, Feb. 18, 2021. [Online]. Available: https://www.bevananda.com/dampak-pandemi-corona-didalam-bisnis-konstruksi/
  22. N. Islamiati and Y. D. Suwandari, “Analisis Faktor Supply Material Terhadap Keterlambatan Proyek Di Era Pandemi Covid-19 (Studi Kasus Jalur Pedestrian Kandang Roda – Pakansari),” J. Tek. Sipil, vol. 2, no. 2, pp. 245–252, 2021, doi: https://doi.org/10.31284/j.jts.2021.v2i2.2306.
  23. Hermanto and I. Tani, “Analisis Risiko Dan Mitigasi Risiko Keterlambatan Pembangunan Menara Telekomunikasi Pada Pt.Xyz,” in Prosiding CEEDRiMS 2021, 2021, pp. 418–425. [Online]. Available: http://hdl.handle.net/11617/12737
  24. N. Dewi, M. A. Abdurrahman, and S. Hamzah, “Studi Penggunaan Metode Evm ( Earned Value Management ) Pada Pengendalian Biaya Dan Waktu Pada Proyek Pembangunan Mall Grand Daya Square,” Makasar, 2020.
  25. T. A. N. Alenezi, “Covid-19 Causes Of Delays On Construction Projects In Kuwait,” Int. J. Eng. Res. Gen. Sci., vol. 8, no. 4, pp. 35–39, 2020, [Online]. Available: http://pnrsolution.org/Datacenter/Vol8/Issue4/5.pdf
  26. M. A. bin Mohamed, M. F. H. bin Azmi, and S. I. binti M. Sheffie, “COVID-19 Pandemic : The Impacts and Prospects in the Malaysian Construction Projects,” IOP Conf. Ser. Earth Environ. Sci., pp. 1–8, 2021, doi: 10.1088/1755-1315/1067/1/012050.
  27. G. Vitri, W. Boy, and W. P. Zayu, “Analisis Faktor Penyebab Keterlambatan Pelaksanaan Proyek Rehabilitasi Sekolah Dalam Masa Pandemi Covid-19,” Racic Rab Constr. Res., vol. 5, no. 2, pp. 65–74, 2020, doi: 10.36341/racic.v5i2.1543.
  28. N. Maelissa, W. Gaspersz, and S. Metekohy, “Dampak Pandemi Covid-19 Bagi Pelaksanaan Proyek Konstruksi Di Kota Ambon,” J. Simetrik, vol. 11, no. 1, p. 411, 2021, doi: 10.31959/js.v11i1.21.
  29. S. Christarindra and C. B. Nurcahyo, “Analisis Penyebab Keterlambatan Proyek Pembangunan Tower Caspian Grand Sungkono Lagoon,” J. Tek. ITS, vol. 9, no. 2, 2021, doi: 10.12962/j23373539.v9i2.53237.
  30. W. Boy, R. Erlindo, and R. A. Fitrah, “Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Gedung Kuliah Pada Masa Pandemi COVID 19,” J. RIVET (Riset dan Inven. Teknol., vol. 01, no. 01, pp. 57–64, 2021, doi: 10.47233/rivet.v1i01.231.
  31. A. Triyawan and Z. E. U. Fendayanti, “Dampak pandemi covid-19 terhadap keberlangsungan perusahaan jasa konstruksi,” FORUM Ekon. J. Ekon. Manaj. dan Akunt., vol. 23, no. 2, pp. 223–230, 2021, [Online]. Available: https://journal.feb.unmul.ac.id/index.php/FORUMEKONOMI/issue/view/182
  32. K. J. Santoso, K. A. Wijaya, H. P. Chandra, and S. Ratnawidjaja, “Potret Industri Konstruksi Di Surabaya Dalam Masa Pandemi COVID-19,” J. Dimens. Pratama Tek. Sipil, vol. 10, no. 1, pp. 57–64, 2021, [Online]. Available: https://publication.petra.ac.id/index.php/teknik-sipil/issue/view/445
  33. B. R. Suseno, S. N. Sari, and R. Maulana, “Analisis Percepatan Waktu Penyelesaian Proyek Menggunakan Metode Crash Program Dengan Penambahan Jam Kerja Dan Penerapan Sistem Kerja Shift,” 2021, vol. 2021, no. November, pp. 135–145. [Online]. Available: http://journal.itny.ac.id/index.php/ReTII
  34. A. G. Putri and E. D. Kusumastuti, “Analisis Penerapan Biaya Standar terhadap Pengendalian Biaya Produksi pada Javasublim,” Indones. Account. Lit. J., vol. 02, no. 02, pp. 337–346, 2022, doi: https://doi.org/10.35313/ialj.v2i2.3162.
  35. R. P. Utari and A. Samad, “Evaluasi Kinerja Proyek Pembangunan Gedung Akibat Covid-19 Dengan Metode Earned Value Concept ( Evm ),” Semin. Nas. Teknol. dan Rekayasa, vol. 6, pp. 173–181, 2020, doi: https://doi.org/10.22219/sentra.v0i6.3867.
  36. A. Sujarwo and W. Oetomo, “Analisis Waktu dan Biaya Pembangunan Gedung IKFM, IPS, IPL Dan Parkir Kendaraan Karyawan,” J. KACAPURI, vol. 5, no. 1, pp. 269–278, 2022, doi: http://dx.doi.org/10.31602/jk.v5i1.7527.
  37. H. A. Rani, A. M. Farouk, K. S. Anandh, S. Almutairi, and R. A. Rahman, “Impact of COVID-19 on Construction Projects: The Case of India,” Buildings, vol. 12, no. 6, pp. 1–20, 2022, doi: 10.3390/buildings12060762.
  38. M. A. H. Kamarazaly, A. E. Badaruddin, S. C. A. Ling, N. Hashim, L. S. King, and A. M. Yaakob, “The Impact of Coronavirus ( Covid- 19 ) Outbreak Towards Contractors’ Performance In Malaysia,” J. Built Environ. Technol. Eng., vol. 8, no. March, pp. 42–51, 2020.
  39. R. Juniarti, R. Pratiwi, and S. M. Nuh, “Proyek Pembangunan Distribution Center Alfamart Pontianak,” JeLAST J. PWK, Laut, Sipil, Tambang, vol. 8, no. 1, 2021, doi: http://dx.doi.org/10.26418/jelast.v8i1.44613.
  40. D. J. Sasongke, L. Kalangi, J. Akuntansi, F. Ekonomi, U. Sam, and J. K. Bahu, “Analisis Anggaran Biaya Produksi Sebagai Alat Untuk Meningkatkan Efektivitas Pengendalian Biaya Produksi Pada Pt Sari Tuna Makmur,” J. LPPM Bid. EkoSosBudKum, vol. 6, no. 2, pp. 1297–1310, 2023, [Online]. Available: https://ejournal.unsrat.ac.id/v3/index.php/lppmekososbudkum/article/view/45446
  41. Y. S. Rini, A. Kurniawan, and D. Ayu Paramitha, “Analisis Perhitungan Harga Pokok Produksi Pada Masa Pandemi Covid19 Pada Mawaddah Bakery Nganjuk,” 2021, no. 3, pp. 970–977.
  42. Darsono and A. Purwanti, Penganggaran Perusahaan, Kedua. Jakarta: Mitrawacanamedia, 2010.
  43. M. M. Sari, T. S. Hadi, and Aldiansyah, “Faktor penyebab pembengkakan biaya yang berpengaruh terhadap biaya akhir pada proyek konstruksi gedung (,” J. Infrastruktur, vol. 6, no. 1, pp. 59–67, 2020, doi: 10.35814/infrastruktur.v6i1.1335.
  44. B. Darmanto, J. Widjayakusuma, and M. R. A. Simanjuntak, “Identifikasi Faktor-Faktor yang Menyebabkan Cost Overrun pada Konstruksi Gedung Bertingkat,” Pros. Semin. Nas. Tek. Sipil 2020 Fak. Tek. Univ. Muhammadiyah Surakarta, pp. 334–342, 2020, [Online]. Available: http://hdl.handle.net/11617/12165
  45. B. Dwipurwanto, “Identifikasi Faktor-Faktor Penyebab Terjadinya Cost Overrun pada Proyek Konstruksi Gedung di Surabaya,” Publ. Ris. Orientasi Tek. Sipil, vol. 4, no. 1, pp. 7–13, 2022, doi: 10.26740/proteksi.v4n1.p7-13.
  46. I. A. C. V. Laksmi, I. W. Jawat, and N. K. Armaeni, “Peringkat Faktor-Faktor Yang Mempengaruhi Produktivitas Konstruksi Akibat Penyebaran Virus Covid-19,” FROPIL (Forum Prof. Tek. Sipil), vol. 9, no. 2, pp. 78–85, 2022, doi: https://doi.org/10.33019/fropil.v9i2.2432.