Perencanaan Control Valve Pada Head Tank PLTA Tulungagung Menggunakan PLC

Authors

  • Mohammad Noor Hidayat Politeknik Negeri Malang
  • Elan Causa Nursal PT. PLN Nusantara Power
  • Ferdian Ronilaya Politeknik Negeri Malang
  • Muhammad Fahmi Hakim Politeknik Negeri Malang

DOI:

https://doi.org/10.33795/elposys.v10i2.2676

Keywords:

head tank, water level, modification, control valve, PLC, SCADA

Abstract

Head Tank of the Tulungagung Hydro Electric Power Plan of PT PJBUP Brantas still has a manual control valve which consists of  a gate valve and a pair of  float valves. There are some problems when the pipe of the float valve is blocked by cediment and debris, it could affect the cooling water system and make damage to the power plant. In this research, there would build a plan of the automatic control valve of the Tulungagung HEPP. PLC Siemens Simatic Step 7 was used as a control base on a SCADA software Wonderware Intouch version 10.0.0. In this modification plan, a pair of float valve changed over solenoid valve and manual gate valve change over motorized valve. For the water level that would be ultrasonic sensor SICK UM 30 as a input for the power meter Omron Procces Meter K3MA-J. The reliability of this modification are excellence and complete for the auto/manual control even for the long distance one. Moreover this modification also has excellence safety.

References

Alvaro Luiz G. Carneiro, Almir C. S. Porto Jr., An Integrated Approach for Process Control Valves Diagnosis Using Fuzzy Logic, Nuclear Energy Research Institute/National Nuclear Energy Commission (IPEN/CNEN—SP), Navy Technology Center/Navy Ministry (CTMSP/MB), Sau Pulo, Brazil, 2014

Indar Sugiarto, Design and Implementation of SCADAlarm in A Drink Production Process Using Wonderware, Electrical Engineering Department, Faculty of Industrial Technology, Petra Christian University, Surabaya, 2004

Mohammad HEIDARI, Hadi HOMAEI, Improving The Pneumatic Control Valve Performance Using A PID Controller, Mechanical Engineering Group, Aligudarz Branch, Islamic Azad University, Faculty of Engineering, Shahrekord University, Shahrekord, Iran, 2015

Panos J. Antsaklis, Kevin M. Passino, S. J. Wang, An Introduction to Autonomus Control System, Greece, Angola, Taiwan, 1991

PLTA Tulungagung PT PJB UP Brantas, Instruksi Kerja (IK) Main Strainer PLTA Tulungagung, Desa Besole, Tulungagung, 2017.

PLTA Tulungagung PT PJB UP Brantas, Standart Operasional Procedure (SOP) Head tank PLTA Tulungagung, Desa Besole, Tulungagung, 2012.

PLTA Tulungagung PT PJB UP Brantas, Standart Operasional Procedure (SOP) Head tank PLTA Tulungagung, Desa Besole, Tulungagung , 2012.

Reivax, RTX Power, Voltage Regulator and Speed Govenor Integrated System,” Operation and Maintenance Manual”, Golang, Ngebel dan Siman, 2015.

Richa Netto, Aditya Bagri, Programmable Logic Controllers, Thadomal Shahani Engineering College, Mumbai University Bandra, Mumbai, 2013.

Rizkika Fitri, Erik Haritman, Dede Suparta, Wawan Purnama, SCADA Untuk Twido Trainer Menggunakan Perangkat Lunak Wonderware Intouch, Program Studi Pendidikan Teknik ElektroFPTK Universitas Pendidikan Indonesia, Bandung 2013

Tim PT PLN (Persero) Udiklat Padang, Materi Khusus Teknisi Pembantu Listrik PLTA (Modul I Pemeliharaan), Tim PT PLN (Persero) Udiklat Padang, Padang, ± 2007

Sigit Setya Wiwaha, Ferdian Ronilaya, Farhan Dhiya Ulhaq, M. Naufal Fariz Muhfid, Ricky Setyawan, and Sri Wahyuni Dali, “Rancang Bangun Turbin Crossflow Pada Spiral Vortex Turbine House Sebagai Pembangkit Listrik Tenaga Pikohidro”, elposys, vol. 8, no. 3, Oct. 2021.

Andrik Sunyoto, Priya Surya Harijanto, and Bakti Indra Kurniawan, “Sistem Instalasi Pembangkit Pikohidro Untuk Keluaran Listrik Arus Searah 12 Volt”, elposys, vol. 9, no. 3, pp. 99–107, Feb. 2022.

Rhezal Agung, Naufal Ramadhani Akbar, and Sapto Wibowo, “Perencanaan dan Implementasi Inverter Satu Fasa Pada Pembangkit Listrik Tenaga Pikohidro di Air Terjun Watu Lumpang Mojokerto”, elposys, vol. 9, no. 3, pp. 108–114, Oct. 2022.

Hasibuan, B. A., Siahaan, J. C., & Harianda, I. (2022). ANALISIS UNJUK KERJA TURBIN AIR KAPASITAS 3× 6 MW PADA BEBAN NORMAL DAN BEBAN PUNCAK DI UNIT PLTA PAKKAT PT. ENERGY SAKTI SANTOSA. SINERGI POLMED: Jurnal Ilmiah Teknik Mesin, 3(1), 13-22.

Downloads

Published

2023-06-14

How to Cite

Hidayat, M. N., Nursal, E. C. ., Ronilaya, F., & Muhammad Fahmi Hakim. (2023). Perencanaan Control Valve Pada Head Tank PLTA Tulungagung Menggunakan PLC. Elposys: Jurnal Sistem Kelistrikan, 10(2), 130–135. https://doi.org/10.33795/elposys.v10i2.2676