Perancangan dan Analisis Tekno Ekonomi PLTS On-Grid System sebagai Supply Energi Listrik Masjid Al-Istiqamah Politeknik Negeri Jember
DOI:
https://doi.org/10.33795/elposys.v11i3.4609Keywords:
On-Grid, PLTS, PVSyst, savings, techno economicsAbstract
The increasing energy demand is directly proportional to the growing population and technological advancements. The energy needs in Indonesia largely rely on fossil fuels, which are limited and environmentally unfriendly due to their emission characteristics. The potential of solar energy in Indonesia is around 4.8 kWh/m2, making it a renewable and environmentally friendly energy source that can be utilized for Solar Power Plants (PLTS). The aim of this research is to design an on-grid PLTS system and conduct techno-economic analysis using PVSyst software. This design requires 14 Longi Solar/LR5-72HPH-550M solar panels and 1 Huawei SUN2000-6KTL-M1 inverter. The estimated electricity production is 10,852 kWh/year in the first year. The initial investment cost for this PLTS system is Rp. 120,343,517.00, with estimated savings over 25 years amounting to Rp. 270,115,412.00. Economically, based on the feasibility analysis using the LWBP tariff calculation method, the NPV is Rp. 2,174,707.00, BCR is 1.68, and PBP is 11.8 years. Meanwhile, based on the feasibility analysis using the LCoE calculation method, the NPV is Rp. 74,877,690.00, BCR is 2.61, and PBP is 7.5 years. Based on the conducted research, the construction of this PLTS is deemed feasible to be implemented.
References
R. Hammam, “Outlook energi indonesia 2021 perspektif teknologi energi indonesia: tenaga surya untuk penyediaan energi charging station,” Jakarta: Pusat Pengkajian Industri Proses dan Energi (PPIPE), Badan Pengkajian dan Penerapan Teknologi (BPPT), 2021.
KESDM.. Statistik Ketenagalistrikan Tahun 2020. Jakarta: Sekretariat Direktorat Jenderal Ketenagalistrikan. 2020
KESDM. Data Inventory Emisi GRK Sektor Energi. Jakarta: Pusat Data dan Teknologi Informasi Energi dan Sumber Daya Mineral Kementerian Energi dan Sumber Daya Mineral. 2016
KESDM. Rencana Strategis Kementerian Energi Dan Sumber Daya Mineral. Jakarta: Kementerian Energi dan Sumber Daya Mineral. 2015
Adi,,A. C., F. Lasnawatin, A. B. Prananto,,V. M. Suzanti, I. G. Anutomo, D. Anggreani, M. Yusuf, L. Ambarsari, dan H. Yuanningrat. Handbook of.Energy & Economic.Statistics of Indonesia,(Final Edition). Ministrynof Energynand Mineral Resource Republicnof Indonesia. 2018
PLN. Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) PT PLN (Persero) 2021-2030. Jakarta. 2021.
Jamaaluddin. Buku Petunjuk Pengoperasian Pembangkit Listrik Tenaga Surya (PLTS). Sidoarjo: UMSIDA Press. 2021.
BSN.n2011. PersyaratanmUmum InstalasimListrik 2011 (PUIL 2011).nJakarta: BadannStandarisasinNasional.
Council,nC. E. nGrid connectednsolar PVnsystem (no batterynstorage) design.guidelines for.accredited installers. 2013.
GSES. “Grid-Connected PV Systems: Design and Installation 8". https://www.gses.com.au/wp-content/uploads/2020/03/GCPV- Updates_version-8.pdf. 2020.
Gumintang,mM., M. Sofyan,mdan I. Sulaeman. Designnand Controlnof PVnHybrid System.in Practice..Jakarta: Gesellschaftnfür InternationalenZusammenarbeit (GIZ). m2020.
ICED. 2020. Panduan Perencanaan Dan Pemanfaatan PLTS Atap Di Indonesia. Jakarta.
KESDM. Peraturan Menteri Energi dan Sumber Daya Mineral Nomor 28 Tahun 2016. Jakarta: Kementerian Energi dan Sumber Daya Mineral. 2016.
KESDM. Perubahan Atas Peraturan Menteri Energi dan Sumber Daya Mineral Nomor 49 Tahun 2018. Jakarta: Kementerian Energi dan Sumber Daya Mineral. 2019.
KESDM. Panduan Pengelolaan Lingkungan Pembangkit Listrik Tenaga Surya (PLTS). Jakarta: Sekretariat Direktorat Jenderal Ketenagalistrikan. 2020.
NASA,mmm“Power DatammmAccess Viewer.” https://power.larc.nasa.gov/data-access- viewer/ (Diakses tanggal 10 Januari 2022)..
KESDM. 2022. Energi Baru Terbarukan Berperan Besar Dalam Upaya Penurunan Emisi di Sektor Energi. https://www.esdm.go.id/id/media-center/arsip-berita/energi-baru-terbarukan-berperan-besar-dalam-upaya-penurunan-emisi-di-sektor-energi (Diakses pada 10 Januari 2023).
F. F. Wibowo, M. Rokhmat, and A. Aripriantoni, “Efek Penempatan Panel Surya Terhadap Produksi Energi Pembangkit Listrik Tenaga Surya Cirata 1 Mw,” eProceedings of Engineering, vol. 6, no. 2, 2019.
I. K. A. Setiawan, I. N. S. Kumara, and I. W. Sukerayasa, “Analisis Unjuk Kerja Pembangkit Listrik Tenaga Surya (Plts) Satu MWP Terinterkoneksi Jaringan di Kayubihi, Bangli,” Teknologi Elektro, vol. 13, no. 1, 2014.
I. B. K. Sugirianta, I. G. N. A. D. Saputra, and I. G. A. M. Sunaya, “Modul praktek PLTS on-grid berbasis micro inverter,” Matrix: Jurnal Manajemen Teknologi Dan Informatika, vol. 9, no. 1, pp. 19–26, 2019.
G. H. Sihotang, “Perencanaan Pembangkit Listrik Tenaga Surya Rooftop di Hotel Kini Pontianak,” Journal of Electrical Engineering, Energy, and Information Technology (J3EIT), vol. 7, no. 1, 2019.
G. Riawan, I. N. S. Kumara, and W. G. Ariastina, “Analisis Performansi dan Ekonomi PLTS Atap 10 kWp pada Bangunan Rumah Tangga di Desa Batuan Gianyar,” Majalah Ilmiah Teknologi Elektro, vol. 21, no. 1, p. 63, 2022.
R. Sianipar, “Dasar Perencanaan Pembangkit Listrik Tenaga Surya,” Jetri: Jurnal Ilmiah Teknik Elektro, 2014.
[7]R. Rafli, J. Ilham, and S. Salim, “Perencanaan dan Studi Kelayakan PLTS Rooftop Pada Gedung Fakultas Teknik UNG,” Jambura Journal of Electrical and Electronics Engineering, vol. 4, no. 1, pp. 8–15, 2022.
M. N. Qosim and R. Hariyati, “Kajian Kelayakan Finansial Fotovoltaik Terintegrasi On Grid Dengan Kapasitas 20 kWp,” Kilat, vol. 10, no. 1, pp. 1–9, 2021.
T. G. V. S. Putra, “Analisa Unjuk Kerja Pembangkit Listrik Tenaga Surya 15 KW Di Dusun Asah Teben Desa Datah Karangasem,” Skripsi, Universitas Udayana, 2015.
E. A. Karuniawan, “Analisis Perangkat Lunak PVSYST, PVSOL dan HelioScope dalam Simulasi Fixed Tilt Photovoltaic,” Jurnal Teknologi Elektro Universitas Mercubuana, vol. 12, no. 3, pp. 100–105, 2021.
[11]B. Purwoto, “Efisiensi Penggunaan Panel Surya sebagai Sumber Energi Alternatif,” Emitor: Jurnal Teknik Elektro, vol. 18, pp. 10–14, Mar. 2018, doi: 10.23917/emitor.v18i01.6251.
A. W. Hasanah, R. Hariyati, and M. N. Qosim, “Konsep Fotovoltaik Terintegrasi On Grid dengan Gedung STT-PLN,” Energi & Kelistrikan, vol. 11, no. 1, pp. 17–26, 2019.
E. Tarigan, “Simulasi optimasi kapasitas PLTS atap untuk rumah tangga di Surabaya,” Multitek Indonesia: Jurnal Ilmiah, vol. 14, no. 1, pp. 13–22, 2020.
A. V. Fadilla, M. A. H. Prakoso, Nurhayati, M. N. Hidayat, and A. Hermawan, “Rancang Bangun Passive Photovoltaic 50 Wp Di Laboratorium Energi Terbarukan Politeknik Negeri Malang,” Elposys: Jurnal Sistem Kelistrikan, vol. 7, no. 3, pp. 21–26, 2020, Accessed: Mar. 06, 2023. [Online]. Available: https://jurnal.polinema.ac.id/index.php/elposys/article/view/664
I. B. Kurniansyah, F. Ronilaya, and M. F. Hakim, “Real Time Monitoring System Dari Active Solar Photovoltaic Tracker Berbasis Internet Of Things,” ELPOSYS: Jurnal Sistem Kelistrikan, vol. 7, no. 3, pp. 7–13, 2020.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2024 Elposys: Jurnal Sistem Kelistrikan
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.