Analisis Perbaikan Sistem Pentanahan Tower 70 kV pada Transmisi Wlingi - Blitar

Authors

  • Budi Eko Prasetyo Politeknik Negeri Malang
  • Ahmad Hermawan Politeknik Negeri Malang
  • Safira Azizah Politeknik Negeri Malang

DOI:

https://doi.org/10.33795/elposys.v9i3.970

Keywords:

Ground Resistance, ATP Draw, Electrode, Lightning Arrester, Traveling Wave, BIL (Basic Insulation Level), Transformer

Abstract

High Voltage Air Line (in Indonesian known as SUTT) is defined as part of an electric power transmission network that is likely to be struck by lightning. This condition may lead to back flashover (BFO) phenomenon if the grounding value in the transmission is found to be high (>5 Ohms) and may also generate equipment failure. This research was intended to analyze the grounding improvement in tower T17, so that traveling-wave voltages may not result in failure of the main equipment at the substation, specifically the transformer. The value of the traveling wave at the substation was measured through simulation by means of the ATP Draw application in tower T17 to the substation. The grounding value may be reduced by increasing and widening the distance between the electrodes. The value obtained by modeling 4 electrodes with a distance of 0.5 meter was amounted to 1.73 Ohms. Furthermore, modeling 3 electrodes with a distance of 1 meter had successfully generated a value of 1.06 Ohm, and a value of 1.67 Ohm was also successfully obtained through modeling 2 electrodes with a distance of 2 meters. The ground resistance with a value of 67.05 Ohms that has not been repaired will lead to back flashover (BFO) caused by lightning strikes. However, this may be reduced properly with a lightning arrester which is capable of cutting the overvoltage at the substation, so that the voltage entering the transformer is below the BIL (Basic Insulation Level) value.

References

Artono, A. (2001). Teknik Tegangan Tinggi. Pradnya Paramita.

Aslimeri. (2008). Teknik Transmisi Tenaga Listrik Jilid 2 Untuk SMK. Jakarta: Direktorat Pembinaan Sekolah Menengah Kejuruan.

Hurauruk, T. S. (1987). Pengetanahan Netral Sistem Tenaga Dan Pengetanahan Peralatan. Gelora Aksara Pratama.

Persyaratan Umum Instalasi Listrik 200 (PUIL 2000). (n.d.). Jakarta: Yayasan PUIL

Zoro, R. (2018). Sistem Proteksi Petir Pada Sistem Tenaga Listrik. Remaja Rosdakarya.

Bewley, L. V. 1933. Travelling Waves on Transmission Systems. London: Chapman & Hall, Limited.

Hutauruk, T.S. 1988. Gelombang Berjalan Dan Proteksi Surja, Jakarta. Erlangga.

Suswanto, D. (n.d.). Sistem Distribusi Tenaga Listrik

. Jian, L. (2008). Study On Measuring Grounding Resistance Of Grounding Grid With Short Lead Wire. China International Conference on Electricity Distribution, 2-5.

Jumari. (2019). Sistem Pengetanahan Pada Jaringan Distribusi Di PT.PLN (Persero). Universitas Darma Agung.

Keputusan Direksi Saluran Udara Tegangan Tinggi dan Ekstra Tinggi (SUTT/SUTET). (2014). PT PLN (Persero).

Mardi, A. (2013). Analisa Perbaikan Pentanahan Kaki Menara Transmisi 150 kV Rembang-Blora Bertahanan Tinggi Dan Usaha Menurunkannya. Politeknik Negeri Bandung, 6-33.

MM, I. J. (2017). Petunjuk Praktis Perancangan Pentanahan Sistem Tenaga Listrik. Sidoarjo: Universitas Muhammadiyah

Sidoarjo.

Rong, Z. (2004). Grounding Resistance Meansurement Analysis Of Grounding System In Vertical_layered Soil. IEEE Transactions On Power Delivery, 19.

Saputro, N. H. (2016). Analisis Pentanahan Kaki Menara Transmisi 150 KV Rembang-Blora Bertahanan Tinggi Dan Usaha Menurunkannya. Universitas Muhammadiyah Surakarta, 15.

Downloads

Published

2022-10-28

How to Cite

Prasetyo, B. E., Hermawan, A., & Azizah, S. . (2022). Analisis Perbaikan Sistem Pentanahan Tower 70 kV pada Transmisi Wlingi - Blitar. Elposys: Jurnal Sistem Kelistrikan, 9(3), 205–209. https://doi.org/10.33795/elposys.v9i3.970