Studi Kinerja Relay Proteksi pada Transformator II 150/20 KV 50 MVA dengan Penyulang Lakarsantri di GIS Karangpilang PT. PLN (Persero) UPT Malang ULTG

Authors

  • Rhezal Agung Ananto Politeknik Negeri Malang
  • Budi Eko Prasetyo Politeknik Negeri Malang
  • Ummu Hanik Politeknik Negeri Malang
  • Riska Salsabila Sugiarto Politeknik Negeri Malang

DOI:

https://doi.org/10.33795/elposys.v8i2.633

Keywords:

Coordination, Protection, Relay, Transformator

Abstract

The substation is one of the components of the electric power system that is an important role in the distribution of
electrical energy and load regulation. In the process of distributing electrical energy, continuity of good service is needed, but the
interferences still often occur, both internal and external. On Sunday, July 21, 2019 there was an interference, Lakarsantri feeder CB failed to trip so make the incoming 20kV CB trip. That interference was caused by the burning of the Switching Substation in the Citraland area. Therefore, a new relay setting is needed as a recommendation to use transformator 2 to avoid the recurrence of a similar fault. The relay settings have shown good results where the working time of the relay on the outgoing feeder side is faster than the incoming feeder 20kV and the incoming transformator 150kV side, when coordination simulated using the E-TAP 12.6.0 software by entering the current setting and the time setting, it shows good coordination because when there is an interference on the outgoing feeder, CB outgoing feeder works first, not the incoming feeder 20kV CB or the incoming transformator 150kV CB. Preventive maintenance on other equipment such as CB and CT need to be be done to increase of equipment reliability to reduce the occurs of protection failure or damage to the equipment.

References

Titarenko, M., dkk. Protective Realiying in Electric Power. Moscow: Peace Publisher

Tleis, Nasser. (2008). Power Systems Modelling and Fault Analysis, Oxford: Elsevier Ltd

Karyana, dkk. (2013). Pedoman dan Petunjuk Sistem Proteksi Transmisi dan Gardu Induk Jawa Bali. Jakarta: PT. PLN (persero)

Pramika, Asda. (2017). Analisis Koordinasi Proteksi pada Trafo 5 150/20 kV 60 MVA Penyulang Doho dan Ngadiluwih di Gardu Induk Banaran Kota Kediri. Skripsi. Malang,Indonesia : Politeknik Negeri Malang

Fauzan, Mochamad Irfani, dkk. “Analisis Reseting Rele Arus Lebih Akibat Perubahan Transformator Daya dan Penambahan Penyulang di Gardu Induk Srondol Semarang,” Transient. vol.5. Semarang: Universitas Diponegoro, 2016, pp. 433-440.

Dewangga, Ananta Setia. (2015). Studi Koordinasi Proteksi Rele Arus Lebih, Diferensial, dan Ground Fault pada PT. Linde Indonesia Cilegon. Skripsi. Surabaya,Indonesia: Institut Teknologi Sepuluh Nopember

Upanayana, I Nyoman, dkk. “Pemasangan DGR (Directional Ground Relay) untuk Mengatasi Gangguan Sympathetic Trip pada GIS Bandara Penyulang Ngurah Rai I dan Ngurah Rai II,” Teknologi Elektro. Vol.16. pp. 118-123

Primawati, Era. (2019). Analisa Pengaturan Proteksi Rele Diferensial Pada Trafo III 60 MVA di Gardu Induk Banyudono 150kV/20kV. Skripsi. Surakarta, Indonesia: Universitas Muhammadiyah Surakarta

Downloads

Published

2021-06-30

How to Cite

Ananto, R. A., Prasetyo, B. E., Hanik, U. ., & Sugiarto, R. S. . (2021). Studi Kinerja Relay Proteksi pada Transformator II 150/20 KV 50 MVA dengan Penyulang Lakarsantri di GIS Karangpilang PT. PLN (Persero) UPT Malang ULTG. Elposys: Jurnal Sistem Kelistrikan, 8(2), 57–65. https://doi.org/10.33795/elposys.v8i2.633